The Influence of Optimism Bias on Time and Cost on Construction Projects

Aaron Chadee, Salisha R. Hernandez, Hector Martin

Abstract


The unresolved scholarly debate to curtail cost and time performances in projects has led to alternate solutions, departing from the dominant technical school of thought to include concepts from behavioural sciences. In this paper, we consider the psychological effect, namely optimism bias, as one of the root causes for delays in cost overruns on projects. The research objectives were to determine the level of bias among project participants, rank time and cost overrun causes according to the participants’ bias score and establish a mitigation strategy to curb potential delays and cost overrun impacts based on the bias scores obtained. A literature survey was conducted to determine causal factors contributing to delays and cost overruns linked to optimism bias. Through a pilot survey of three semi-structured interviews, eighty factors obtained from the literature survey were reduced to 24 critical delay and cost overrun factors relevant to Trinidad and Tobago. A questionnaire was subsequently developed seeking construction professionals to rate their bias scores based on an 11-point Likert scale. The research confirms that project planners and decision-makers exhibit moderate levels of optimism bias; however, participants lacked awareness of the impact of optimism bias on projects outcomes. Project location, environmental impacts and historic preservation, and labour disputes are the top three critical factors where project professionals displayed increased optimistic tendencies. It is proposed that contingency “time window” and reference class forecasting be implemented as control mechanisms to mitigate the impacts of time and cost overruns on projects. This research introduces a novel method to account for and measure optimism bias on construction projects. This study adds knowledge into delays and cost overruns causation and provides a foundation for future studies on quantifying psychological effects on projects and enhancing overall project management practices.

 

Doi: 10.28991/esj-2021-01287

Full Text: PDF


Keywords


Construction Projects; Optimism Bias; Delays; Cost Overrun; Consequences; Mitigation Strategy.

References


Aibinu, Ajibade Ayodeji, and Henry Agboola Odeyinka. “Construction Delays and Their Causative Factors in Nigeria.” Journal of Construction Engineering and Management 132, no. 7 (July 2006): 667–677. doi:10.1061/(asce)0733-9364(2006)132:7(667).

Simtette, J. "Accounting for Megaproject Dollars." Public roads 68, no. 1 (2004): 40-47.

Taxpayers Alliance. "Beyond the Dome: Government Projects £23 Billion Over Budget." Available online: https://d3n8a8pro7vhmx.cloudfront.net/taxpayersalliance/pages/2038/attachments/original/1438685061/Beyond_the_Dome.pdf?1438685061(accessed on July 2019).

Son, JeongWook, and Eddy M. Rojas. “Impact of Optimism Bias Regarding Organizational Dynamics on Project Planning and Control.” Journal of Construction Engineering and Management 137, no. 2 (February 2011): 147–157. doi:10.1061/(asce)co.1943-7862.0000260.

Flyvbjerg, Bent, Nils Bruzelius, and Werner Rothengatter. Megaprojects and risk: An anatomy of ambition. Cambridge University Press, 2003.

Al-Khalil, Mohammed I., and Mohammed A. Al-Ghafly. “Important Causes of Delay in Public Utility Projects in Saudi Arabia.” Construction Management and Economics 17, no. 5 (September 1999): 647–655. doi:10.1080/014461999371259.

Siemiatycki, Matti. “Managing Optimism Biases in the Delivery of Large-Infrastructure Projects: A Corporate Performance Benchmarking Approach.” 2008 First International Conference on Infrastructure Systems and Services: Building Networks for a Brighter Future (INFRA) (2008). doi:10.1109/infra.2008.5439642.

Lovallo, Dan, and Daniel Kahneman. "Delusions of Success: How Optimism Undersmines Executives' Decisions." Harvard Business Review 81, no. 7 (2003): 1-10.

Treasury, H. M. S. "The Green Book-Appraisal and Evaluation in Central Government 2003 TSO." (2003).

Shelbourn, M., N.M. Bouchlaghem, C. Anumba, and P. Carrillo. “Planning and Implementation of Effective Collaboration in Construction Projects.” Construction Innovation 7, no. 4 (October 16, 2007): 357–377. doi:10.1108/14714170710780101.

Emmons, Debra, Thomas Mazzuchi, Shahram Sarkani, and Curtis Larsen. “Mitigating Cognitive Biases in Risk Identification: Practitioner Checklist for the Aerospace Sector.” Defense Acquisition Research Journal 25, no. 1 (January 2, 2018): 52–93. doi:10.22594/dau.16-770.25.01.

Ahiaga-Dagbui, Dominic, Simon D. Smith, Peter ED Love, and Fran Ackermann. "Spotlight on construction cost overrun research: superficial, replicative and stagnated." (2015).

Love, Peter E.D., Dominic D. Ahiaga-Dagbui, and Zahir Irani. “Cost Overruns in Transportation Infrastructure Projects: Sowing the Seeds for a Probabilistic Theory of Causation.” Transportation Research Part A: Policy and Practice 92 (October 2016): 184–194. doi:10.1016/j.tra.2016.08.007.

Asiedu, Richard Ohene, and Ebenezer Adaku. “Cost Overruns of Public Sector Construction Projects: a Developing Country Perspective.” International Journal of Managing Projects in Business 13, no. 1 (May 6, 2019): 66–84. doi:10.1108/ijmpb-09-2018-0177.

Johnson, Reshma Mary, and Robin Itty Ipe Babu. “Time and Cost Overruns in the UAE Construction Industry: a Critical Analysis.” International Journal of Construction Management 20, no. 5 (November 13, 2018): 402–411. doi:10.1080/15623599.2018.1484864.

Flyvbjerg, Bent. "Delusions of success: comment on Dan Lovallo and Daniel Kahneman." Harvard Business Review 81, no. 12 (2003): 121-122.

Flyvbjerg, Bent. “Five Misunderstandings about Case-Study Research.” Qualitative Inquiry 12, no. 2 (April 2006): 219–245. doi:10.1177/1077800405284363.

Flyvbjerg, Bent, Atif Ansar, Alexander Budzier, Søren Buhl, Chantal Cantarelli, Massimo Garbuio, Carsten Glenting, et al. “Five Things You Should Know About Cost Overrun.” Transportation Research Part A: Policy and Practice 118 (December 2018): 174–190. doi:10.1016/j.tra.2018.07.013.

Chadee, Aaron Anil, Xsitaaz Twinkle Chadee, Indrajit Ray, Abrahams Mwasha, and Hector Hugh Martin. “When Parallel Schools of Thought Fail to Converge: The Case of Cost Overruns in Project Management.” Buildings 11, no. 8 (July 27, 2021): 321. doi:10.3390/buildings11080321.

Assaf, Sadi A., and Sadiq Al-Hejji. “Causes of Delay in Large Construction Projects.” International Journal of Project Management 24, no. 4 (May 2006): 349–357. doi:10.1016/j.ijproman.2005.11.010.

Oyewobi, Luqman Oyekunle, Richard Jimoh, Bashir Olanrewaju Ganiyu, and Abdullateef Adewale Shittu. “Analysis of Causes and Impact of Variation Order on Educational Building Projects.” Journal of Facilities Management 14, no. 2 (May 3, 2016): 139–164. doi:10.1108/jfm-01-2015-0001.

Invernizzi, Diletta Colette, Giorgio Locatelli, and Naomi J Brookes. “Cost Overruns – Helping to Define What They Really Mean.” Proceedings of the Institution of Civil Engineers-Civil Engineering 171, no. 2 (May 2018): 85–90. doi:10.1680/jcien.17.00001.

Flyvbjerg, Bent. "Design by deception: The politics of megaproject approval." Harvard Design Magazine, Spring/Summer 22 (2005): 50-59.

Flyvbjerg, Bent, and Eamonn Molloy. "Delusion, deception and corruption in major infrastructure projects: Causes, consequences and cures." The international handbook on the economics of corruption, Cheltenham, UK, Northampton (MA), USA, Edward Elgar 2 (2011): 81-107.

Flyvbjerg, Bent, Massimo Garbuio, and Dan Lovallo. “Delusion and Deception in Large Infrastructure Projects: Two Models for Explaining and Preventing Executive Disaster.” California Management Review 51, no. 2 (January 2009): 170–194. doi:10.2307/41166485.

Flyvbjerg, Bent, Carsten Glenting, and Arne Rønnest. "Procedures for dealing with optimism bias in transport planning." London: The British Department for Transport, Guidance Document (2004).

Dorée, A. G. “Collusion in the Dutch Construction Industry: An Industrial Organization Perspective.” Building Research & Information 32, no. 2 (March 2004): 146–156. doi:10.1080/0961321032000172382.

Chadee, Aaron Anil, Xsitaaz Twinkle Chadee, Abrahams Mwasha, and Hector Hugh Martin. “Implications of ‘Lock-in’ on Public Sector Project Management in a Small Island Development State.” Buildings 11, no. 5 (May 8, 2021): 198. doi:10.3390/buildings11050198.

Chadee, Aaron, Indrajit Ray, and Xsitaaz Chadee. “Systemic Issues Influencing Technical Certainty in Social Housing Programmes in a Small Island Developing State.” Buildings 11, no. 2 (February 12, 2021): 65. doi:10.3390/buildings11020065.

Abd El-Razek, M. E., H. A. Bassioni, and A. M. Mobarak. “Causes of Delay in Building Construction Projects in Egypt.” Journal of Construction Engineering and Management 134, no. 11 (November 2008): 831–841. doi:10.1061/(asce)0733-9364(2008)134:11(831).

Doloi, Hemanta, Anil Sawhney, K.C. Iyer, and Sameer Rentala. “Analysing Factors Affecting Delays in Indian Construction Projects.” International Journal of Project Management 30, no. 4 (May 2012): 479–489. doi:10.1016/j.ijproman.2011.10.004..

Marzouk, Mohamed M., and Tarek I. El-Rasas. “Analyzing Delay Causes in Egyptian Construction Projects.” Journal of Advanced Research 5, no. 1 (January 2014): 49–55. doi:10.1016/j.jare.2012.11.005.

Plotch, Philip Mark. “What’s Taking So Long? Identifying the Underlying Causes of Delays in Planning Transportation Megaprojects in the United States.” Journal of Planning Literature 30, no. 3 (January 8, 2015): 282–295. doi:10.1177/0885412214566116.

Love, P., P. Davis, David Baccarini, Geoff Wilson, and Robert Lopez. "Opening Pandora's Box: Revisiting Procurement Selection in the Public Sector." In The Third Scottish Conference for Postgraduate Researchers of the Built & Natural Environment (PRoBE). 2007.

Love, Peter ED, Peter Davis, David Baccarini, Geoff Wilson, and Robert Lopez. "Procurement selection in the public sector: a tale of two states." (2008).

Uff, J., and D. Thornhill. "Report of the commission of enquiry into the construction sector Trinidad and Tobago." Government of Trinidad and Tobago, Port of Spain, Trinidad and Tobago: Ministry of Finance (2010). Available online: www.jcc.org.tt/uffreport.pdf (accessed on May 2021).

Hickson, Brent G., and Leighton A. Ellis. "Factors affecting construction labour productivity in Trinidad and Tobago." The Journal of the Association of Professional engineers of Trinidad and Tobago 42, no. 1 (2014): 4-11.

Shah, Raj Kapur. “An Exploration of Causes for Delay and Cost Overruns In Construction Projects: Case Study of Australia, Malaysia & Ghana.” Journal of Advanced College of Engineering and Management 2 (November 29, 2016): 41. doi:10.3126/jacem.v2i0.16097.

Ahiaga-Dagbui, Dominic D., and Simon D Smith. “Rethinking Construction Cost Overruns: Cognition, Learning and Estimation.” Journal of Financial Management of Property and Construction 19, no. 1 (April 7, 2014): 38–54. doi:10.1108/jfmpc-06-2013-0027.

Asiedu, Richard Ohene, and Ebenezer Adaku. “Cost Overruns of Public Sector Construction Projects: a Developing Country Perspective.” International Journal of Managing Projects in Business 13, no. 1 (May 6, 2019): 66–84. doi:10.1108/ijmpb-09-2018-0177.

Bakri, Adnan, M.F.M. Alkbir, Nuha Awang, Fatihhi Januddi, M. A. Ismail, Ahmad Nur Aizat Ahmad, and Izatul Husna Zakaria. “Addressing the Issues of Maintenance Management in SMEs: Towards Sustainable and Lean Maintenance Approach.” Emerging Science Journal 5, no. 3 (June 1, 2021): 367–379. doi:10.28991/esj-2021-01283.

Derakhshanalavijeh, Roya, and Jose Manuel Cardoso Teixeira. “Cost Overrun in Construction Projects in Developing Countries, Gas-Oil Industry of Iran as a Case Study.” Journal of Civil Engineering and Management 23, no. 1 (July 13, 2016): 125–136. doi:10.3846/13923730.2014.992467.

Kaliba, Chabota, Mundia Muya, and Kanyuka Mumba. “Cost Escalation and Schedule Delays in Road Construction Projects in Zambia.” International Journal of Project Management 27, no. 5 (July 2009): 522–531. doi:10.1016/j.ijproman.2008.07.003.

Roy, Debopam, and Satyanarayana N. Kalidindi. “Critical Challenges in Management of Heritage Conservation Projects in India.” Journal of Cultural Heritage Management and Sustainable Development 7, no. 3 (September 14, 2017): 290–307. doi:10.1108/jchmsd-03-2017-0012.

Flyvbjerg, Bent. “Curbing Optimism Bias and Strategic Misrepresentation in Planning: Reference Class Forecasting in Practice.” European Planning Studies 16, no. 1 (December 17, 2007): 3–21. doi:10.1080/09654310701747936.

Watts, Logan L., Kelsey Medeiros, Tristan McIntosh, and Tyler Mulhearn. "Decision biases in the context of ethics: Initial scale development and validation." Personality and Individual Differences 153. No. 109609 (January 15 2020). doi:10.1016/j.paid.2019.109609.

Caputo, Andrea. “A Literature Review of Cognitive Biases in Negotiation Processes.” International Journal of Conflict Management 24, no. 4 (September 30, 2013): 374–398. doi:10.1108/ijcma-08-2012-0064.

Shaikh, Fazal Ali, Nasurullah Odhano, and Suaathi Kaliannan. “Performance and Management of Cost in the Construction Industry.” Civil Engineering Journal 6, no. 7 (July 1, 2020): 1368–1374. doi:10.28991/cej-2020-03091554..

Tversky, A., and D. Kahneman. “Judgment Under Uncertainty: Heuristics and Biases.” Science 185, no. 4157 (September 27, 1974): 1124–1131. doi:10.1126/science.185.4157.1124.

Sprinkle, Zachary Joseph. "Heuristics in Construction Project Management." PhD diss., Virginia Tech, 2019. Available online: https://vtechworks.lib.vt.edu/bitstream/handle/10919/87089/Sprinkle_ZJ_T_2019.pdf?sequence=1&isAllowed=y (accessed on May 2021).

van Buiten, M., & Hartmann, A. "Public-private partnerships: cognitive biases in the field." In P. Carrillo, & P. Chinowsky (Eds.), Proceedings of the engineering project organization (EPOC 2013): 9-11 July 2013, Winter Park, Colorado (Working Paper Proceedings; Vol. 2013). EPOS.

Ballard, Herman Glenn. "The last planner system of production control." PhD diss., University of Birmingham, 2000.

Heine, Steven J., and Darrin R. Lehman. “Cultural Variation in Unrealistic Optimism: Does the West Feel More Vulnerable Than the East?” Journal of Personality and Social Psychology 68, no. 4 (1995): 595–607. doi:10.1037/0022-3514.68.4.595.

Breakwell G. M., Fife-Schaw C., and Barneett J., Doing social psychology research-Chapter 3: Measuring Optimistic Bias. John Wiley & Sons, 2008.

Moser, C.A., and G. Kalton. “Survey Methods in Social Investigation” (March 2, 2017). doi:10.4324/9781315241999.

Field, Andy. Discovering statistics using SPSS. London: London: Sage Publications, 2009.

Anastasiadou, Sofia D. "Reliability and validity testing of a new scale for measuring attitudes toward learning statistics with technology." Acta Didactica Napocensia 4, no. 1 (2011): 1-10.

George, Darren. SPSS for windows step by step: A simple study guide and reference, 17.0 update, 10/e. Pearson Education India, 2011.

Rao, Prakash B., and Culas Joseph Camron. "Causes of delays in construction projects-A case study." International Journal of Current Research 6, no. 6 (2014): 7219-7222.

Olawale, Yakubu Adisa, and Ming Sun. “Cost and Time Control of Construction Projects: Inhibiting Factors and Mitigating Measures in Practice.” Construction Management and Economics 28, no. 5 (May 2010): 509–526. doi:10.1080/01446191003674519.

Fischhoff, Baruch, Paul Slovic, and Sarah Lichtenstein. “Knowing with Certainty: The Appropriateness of Extreme Confidence.” Journal of Experimental Psychology: Human Perception and Performance 3, no. 4 (1977): 552–564. doi:10.1037/0096-1523.3.4.552.

Staw, Barry M. “The Escalation of Commitment to a Course of Action.” The Academy of Management Review 6, no. 4 (October 1981): 577. doi:10.2307/257636.

Flyvbjerg, Bent, Mette K. Skamris Holm, and Søren L. Buhl. “How (In) accurate Are Demand Forecasts in Public Works Projects?: The Case of Transportation.” Journal of the American Planning Association 71, no. 2 (June 30, 2005): 131–146. doi:10.1080/01944360508976688.

Kahneman, Daniel. "New challenges to the rationality assumption." Journal of Institutional and Theoretical Economics (JITE)/Zeitschrift für die gesamte Staatswissenschaft (1994): 18-36.

Love, Peter E. D., Chun-Pong Sing, Brad Carey, and Jeong Tai Kim. “Estimating Construction Contingency: Accommodating the Potential for Cost Overruns in Road Construction Projects.” Journal of Infrastructure Systems 21, no. 2 (June 2015): 04014035. doi:10.1061/(asce)is.1943-555x.0000221.


Full Text: PDF

DOI: 10.28991/esj-2021-01287

Refbacks



Copyright (c) 2021 Aaron Anil Chadee, Salisha Hernandez, Hector Hugh Martin